MAINTENANCE
5-2 31 Dec 13
DE-7200VFDCentrifuge
PREVENTIVE MAINTENANCE
Preventive maintenance consists of inspection, cleaning, and lubrication. These routine
procedures will ensure maximum life and trouble-free operation. While the maintenance schedule
presented in this section should remain flexible, modifications should be based on experience
with operating the equipment at your facilities. A maintenance log should be kept to help establish
a preventive maintenance schedule, as well as to monitor and adjust the schedule as necessary
throughout the equipment’s life. When establishing a preventive maintenance schedule, consider
duty cycle, ambient temperature, and operating environment. The recommended preventive
maintenance schedule is presented in the table below.
PREVENTIVE MAINTENANCE SCHEDULE
Inspect feed connection for leaks, and tighten connection flange
hardware as required.
Each shift
Inspect liquid discharge connection for leaks. Tighten connection to
prevent leakage.
Each shift
Remove feed tube, clean interior of pipe, and reinstall. 40 hrs
Remove accumulated solids from interior and exterior of case. 40 hrs or as needed
Remove belt cover, inspect belt for damage, and check/adjust tension. Every 160 hrs
Inspect clutch coupling spider for wear. Every 160 hrs
Grease main bearings.
*
Grease conveyor bearing until grease vents through relief valve. (If
vent plug is installed, remove plug from conveyor bearing journal,
inject grease, and then reinstall vent plug.)
*
Grease bowl and conveyor drive motors.
Check/change conveyor drive gearbox oil.
* Refer to Lubrication Chart for applicable lubricants, quantities, and intervals.