OPERATING INSTRUCTIONS
4-4 30 Sep 13
DE-7200VFDCentrifuge
INITIAL STARTUP (CONT’D)
6. Apply electric power to centrifuge. The following screen will appear (on explosion-proof
cabinet, displayed after purge cycle is completed):
7. Without the centrifuge running, perform the following safety checks to confirm that
connections are correct between control cabinet and centrifuge:
• Operate emergency stop buttons on junction box and control cabinet, and check for
Emergency Stop alarm message on control panel.
• Pull out emergency stop buttons to clear alarm message.
• Tap vibration switch housing horizontally with a rubber or rawhide mallet, and check for
High Vibration Fault message on control panel.
• Press reset button on vibration switch to clear alarm message.
8. Select Cent. Status to display the Status screen below. Select Test A/C, and check that air
conditioner fan rotates in the direction indicated by the label. If not, reverse any two fan motor
leads.
9. Verify that machine is ready for operation. Correct any deficiencies before proceeding with
startup procedure. If condition is satisfactory, click in the upper right corner to return to the
Home screen.
10. Select Setup and then click on Pump Setup to view pump operating information:
11. Configure pump parameters as follows:
a. Input data from the pump and pump motor nameplates.
Correct pump data is critical to achieving the desired feed rate to the